March 6, 2019

This dry dock supports critical maintenance, refits and recommissioning of large seagoing vessels. During preliminary evaluation of the upgraded power distribution equipment, the ABM acceptance testing team uncovered relays for medium voltage gear that had not been programmed.
The relays would not perform as intended without the programmed logic. Breakers would not trip when required, and the system would not safely and properly respond as designed.
With the gear manufacturer and the relay vendor responsible for limited deliverables, the electrical contractor faced an energization deadline without the relay logic needed to complete the necessary acceptance testing.

Related Topics

June 21, 2023
Luxury Hotel Parking Elevates Service and Revenue for Hilton Long Beach

ABM's partnership with Hilton Long Beach has transformed their parking operations, resulting in improved service delivery, increased revenue, streamlined operations,...

February 17, 2023
Unmatched Parking Service at Wichita’s National Airport (ICT)

Wichita's largest and fastest-growing regional airport, ICT, offers top-notch parking services in partnership with ABM, enhancing the overall airport experience...

January 23, 2023
Levi’s Stadium Wows Crowds with LEED Gold and Green Cleaning

Since the world-class stadium's opening day, the San Francisco 49ers have relied on ABM's sports facility management expertise for janitorial...

Need Help Need Help Need
Help?