Operationalizing resilience: 5 questions data center leaders should ask today
Key Takeaways
- Solve power delays with prime generation to work around multiyear grid queues and shift from being passive grid consumers into self-sustaining power producers.
- Prioritize direct self-performance to solve for the shortages and gaps in open technical roles.
- Engage operations 12+ months early to ensure that long equipment lead times don’t result in expired warranties before launch.
Driven by AI expansion and digital transformation, data center strategy has rapidly shifted from real estate acquisition and construction to a multifront operational challenge. Energy procurement is no longer a downstream utility coordination step—it is a critical business bottleneck. Simultaneously, a severe deficit of technical labor threatens execution timelines, commissioning schedules, and continuous uptime.
To evaluate whether your portfolio is prepared for this shift, data center executives responsible for design, construction, and operations should be asking five critical questions.
1. Are our energy timelines dictated by utility delays, or are we actively building bridge-to-prime power solutions?
Prolonged utility interconnection queues, often extending several years, have disrupted traditional site selection. Operators are moving away from established hubs into rural markets with distinct gas pressure, local grid, and municipal constraints.
“Traditional infrastructure is a utility service with additional resources for standby,” observed Tom Altini of ABM Energy & Power Solutions. “What we’re seeing today is clients moving quickly in the direction of gas turbines, natural gas reciprocating engines, microgrids, and generators using those for prime and bridge power as the most reliable resource to get them to megawatts as quickly as they can.”
What to evaluate:
- Are we incorporating hybrid distributed energy resources—such as microgrids, generators, solar arrays, natural gas engines, gas turbines, and Battery Energy Storage Systems (BESS)—to bring megawatts online faster while awaiting grid hookups?
- Once utility grid power arrives, do we have a strategy to transition onsite generation assets into financial hedges against tariff volatility, demand charges, or regional capacity response programs?
“Clients are moving quickly to prime and bridge power as the most reliable resource to get them to megawatts as quickly as they can.” – Tom Altini, Director of Sales, ABM Energy & Power Solutions
2. Is our operational strategy built on direct self-performance or fragmented vendor management?
Focusing exclusively on construction and waiting until 120 to 150 days before Integrated System Testing (IST) to build an operations plan creates severe deployment risks. Relying on basic third-party staffing agencies late in the build cycle often results in fragmented oversight and operational gaps.
Brad Tolbert, Senior Vice President of Sales, ABM Technical Solutions, is seeing clients transitioning to workforce models that close operations and communications gaps, noting, “Before, companies would either outsource to a vendor-management-type solution or do the work within their own company. Now what I’m seeing is a real push for self-performance and less vendor management. If you can have skilled trades that are self-performed and then the occasional OEM vendor management, that type of hybrid solution is really successful.”
ABM is working with clients months ahead of project completion to ensure staffing is in place for critical milestones. Through full-time staffing and by self-performing services, clients gain the level of technical talent required with a deep understanding of each facility.
What to evaluate:
- Does our operations model rely on an engineering partner that directly employs, trains, and manages certified mechanical and electrical technicians?
- Are OEM service contracts reserved strictly for proprietary equipment warranties, while core cross-technology execution is handled by an integrated operations team?
3. How are we building long-term talent pipelines instead of competing in a market where talent is constantly poached?
With an estimated 300,000 open technical roles in data center mechanical and electrical operations over the coming years, hyper-dense builds in rural areas put additional strains on local workforce shortages.
Tolbert said ABM and other companies are approaching this on two fronts. ABM, for example, is upskilling its current staff, expanding career paths, and going into high schools and trade schools.
“We are educating younger talent that there is a solid career with great compensation. The last thing you want to do is have a brand-new technician that’s never been to a data center and is learning by shadowing another technician,” he said, pointing out that the need to raise the value of technical careers is imperative.
What to evaluate:
- Are we engaging early pipeline channels, such as vocational-technical schools, trade institutions, and military transition initiatives like Hiring Our Heroes?
- Do our partners utilize simulated, hands-on lab environments—such as electrical testing and battery labs—so technicians master high-voltage switchgear, certified acceptance testing, and liquid cooling systems before touching live white space?
4. Are we mitigating the risk of expired equipment warranties caused by multiyear supply chain lead times?
Securing uninterrupted operational continuity requires bridging the gap between facility construction, equipment commissioning, and long-term asset management.
Supply chain lead times for large turbines, switchgear, and transformers can stretch two to five years. Pre-purchased equipment often sits idle for months or years, creating scenarios where factory warranties expire right as the site goes live.
ABM’s Satish Jayaram, SVP of ABM Energy & Power Solutions, said that there are steep consequences from not planning for equipment delays and having people in place to do the work. “Having iron on the ground doesn’t deliver outcomes to customers if it’s not operating and delivering power to a facility. We have designed our business to deliver outcomes, so we perform engineering, stamp and seal drawings, procure, construct, operate, maintain, and test under a self-performance model.”
Advance planning and the right technical talent provide both expertise and practical knowledge to review equipment and warranty expirations to ensure everything is ready to go when it is needed.
What to evaluate:
- Are operational engineers involved 12 to 18 months before target commissioning to review electrical design for long-term serviceability?
- Are we executing certified acceptance testing and standardized asset management protocols prior to energization to protect equipment longevity and performance?
“The most expensive data center is one that’s not operating. If you don’t commission reliability at the end of the project, you’ve got to design it from the beginning.” – Satish Jayaram, Senior Vice President, ABM Energy & Power Solutions
5. Can our capital models and community engagement strategies unlock faster power scaling?
Navigating energy deployment requires balancing capital allocation with local community alignment to prevent regulatory and financial bottlenecks. One opportunity is to explore alternative models to free up growth capital.
What to evaluate:
- Have we explored off-balance-sheet financing models for prime power and backup assets to preserve balance sheet capital for core computing infrastructure?
- Are we engaging local utilities, community leaders, and municipal boards early to position our power assets as community grid stabilizers during peak demand events?
Strategic path forward
The urgency to solve for power, lifecycle asset management, and technical staffing is accelerating. Data center leaders who integrate self-performing operations partners early, embrace flexible power architectures, and invest in lab-trained talent will secure a distinct competitive advantage in time-to-market and portfolio resilience.